Work Underway at Bridlington Town Hall

Work Underway at Bridlington Town Hall

Work Underway at Bridlington Town Hall

Following a tender award via the YORbuild2 Framework, the project commenced this month at Bridlington Town Hall.

This challenging 44 week programme, is being carried out whilst the site is live will encompass some of the following elements over 4 Phases:-

  • Dilapidation Surveys
  • Scaffolding
  • Crittal Window Repairs
  • Asbestos Surveys
  • High Level Services
  • Repairs and Decoration
  • Structural Alterations
  • Low Level Service Install
  • New IPS Systems
  • Timber Floor Repairs
  • Plastering Repairs
  • External Clean
  • Rooflight Replacement

 

Project Information

Value

£2,080,000

Location

Bridlington

Duration

44 weeks